Until 2021, every stand we sold left Abidjan on a truck. Dakar, Accra, Lomé, Lagos — the stand was cut, finished and packed in our workshop, then driven or shipped to the venue with two of our carpenters following on a plane. It worked, in the way that expensive, fragile things work until they don't. This is a short note on why we stopped, and what replaced it.
The trigger was not one disaster. It was the accounting. When we closed the books that year, transport and border costs were eating 19 % of an average cross-border project — freight, customs brokerage, insurance, the buffer days we had to build into every schedule, and the hotel nights for the escort crew. The client paid for all of it and got nothing visible in return. No better finish, no extra square metre. Just a truck.
What a border does to a schedule
Freight between two ECOWAS capitals looks simple on a map and is anything but on a calendar. A stand travelling from Abidjan to a hall in Accra crossed one border, two inspection points and at least one weighbridge. Our median crossing time in 2021 was 31 hours; our worst was six days. When a show opens on a fixed Tuesday, a six-day tail risk is not a logistics problem — it is a design constraint. We were quietly designing stands to survive customs, not to serve the client's brief.
- Panels were built heavier than the design needed, to survive double handling
- Joinery was simplified so a stand could be re-assembled by a tired crew at 02:00
- Finishes were chosen for durability in a container, not for how they read under hall lighting
The switch to local benches
Between 2021 and 2023 we set up eight local fabrication teams, one per country we serve — Ivory Coast, Senegal, Mali, Burkina Faso, Ghana, Togo, Benin and Nigeria. Each team is a small bench: a lead carpenter we trained in Abidjan, two to four locals, and a rented or shared workshop close to the main venues. Design and engineering stay centralised in Abidjan; drawings, cutting lists and finish specs travel as files, not freight.
What crosses the border now is a PDF. The timber, the paint and the labour are sourced where the show happens. Our cost of delivery on a cross-border stand dropped by roughly a fifth, and we handed that back in the flat rate — it is the reason we can hold 600 € TTC per m² in all eight countries instead of quoting freight case by case.